December 6, 2021
Construction Update November 2021

Maine Township Referendum Project

November 2021 Update

TABLE OF CONTENTS

Neighbor Relations

Project Summary

 

NEIGHBOR RELATIONS

No neighbor issues to report.

 

PROJECT SUMMARY

Current Progress

Work continues as planned. Ongoing activities in the fully occupied schools has been well coordinated by the District to not impact educational function. Punch list work as well as commissioning of MEP systems are also ongoing and depending on lead time of late / replacement material will most likely not be finalized until Winter Break.

Maine East: Area A attic work continues as well as vertical shafts on Level 3 and 2. Starting the Mechanical, Electrical and Plumbing install during the school year helps get a head start on infrastructure replacement in advance of the summer construction season. Work in the Area A classrooms will not occur until summer.

Punch List and Commissioning progress continues with a major push happening over Winter Break.

Maine South: Misc. flooring and interior corridor brick washing wrapped up over Thanksgiving Break. Misc. electrical infrastructure in Back of House locations continues while school is in session.

Punch List and Commissioning progress continues with a major push happening over Winter Break.

Maine West: The Rotunda Lower Level and 1st floor finishes are progressing well with millwork, tile and painting proceeding in both areas. Area is scheduled to wrap up at Winter Break.

B Wing Gym new structure has been completed and walls are being installed as are mechanical, electrical, plumbing and fire protection rough in. Exterior masonry patching is also wrapping up at this time. Area continues to make good progress.

D Wing Canopy security gate installation is ongoing.

COVID 19 Impacts – Weekly Owner / Architect / Contractor Coordination remains remote via Google Meetings, but the District and Wight continue to be present at each campus as needed to resolve issues and monitor the progress of the work.

Construction Budget – Budget and Phasing updates provided as part of the September meeting.

Bid Period No. 3 Design Bid Period 3 was presented at November Buildings and Grounds Meeting for approval. Contracts being executed with Prime Trade Contractors and procurement activities are commencing.