January 2022 Construction Update

TABLE OF CONTENTS

Neighbor Relations
Project Summary 

I.   NEIGHBOR RELATIONS

No neighbor issues to report.

II.   PROJECT SUMMARY

Current Progress

Work continues at Maine West. Multiple meetings with users groups for the balance of the work to be bid. And we are in preparation mode for the Summer 2022 construction program.

Maine East:

Punch list activities performed over Winter Break. Work in the Attic of Area A continues. We will recommence major renovations in the Spring.

Maine South:

Punch List activities performed over Winter Break. Miscellaneous Electrical Work continues. We will recommence major renovations in the Spring.

Maine West:

The Rotunda is now occupied by the school.

Now that the Rotunda is occupied C Wing Gym Renovation has commenced.

B Wing Renovation has finishes that are ongoing with flooring, painting and ceilings.

COVID 19 Impacts

Weekly Owner / Architect / Contractor Coordination remains remote via Google Meetings, but the District and Wight continue to be present at each campus as needed to resolve issues and monitor the progress of the work.

 

Construction Budget

Budget and Phasing provided during the January B&G meeting.

Bid Period No. 4 Design

Bid Period No. 4 design development documents were completed in mid December. District, Wight, PCC and subconsultants had multiple meetings to review PCC’s cost estimates associated with the DP4 work. Design continues by Wight leading to a February bid period with a March Building and Grounds presentation.