Maine Township Referendum Project
July 2023 Update
TABLE OF CONTENTS
- Neighbor Relations
- Project Summary
- Photos
NEIGHBOR RELATIONS
No neighbor issues to report.
PROJECT SUMMARY
Current Progress
Maine East:
Pool – passed all inspections and was turned over to the school.
Area B – Ceiling Grid is currently being installed on all three floors. All overhead mechanical piping & wiring is complete and ceiling trim is continuing to be installed behind the ceiling. Floor prep has started, and flooring is starting to be installed.
Auditorium – House lighting and new can lights are installed and new sprinkler piping and fire alarm is complete. Plaster patching and final paint is wrapping up for the scaffolding to be removed this week. Once the scaffolding is removed all stage rigging work will begin.
Exterior Sitework – All exterior site work is complete.
Maine South:
Auditorium/Stage/Backstage: ADA ramps in the auditorium have been installed. The catwalk support beams is installed and working on misc. steel work. The backstage demo is complete and MEP rough-in is ongoing. Theatre lighting and controls are completed.
North & South Mezzanines: New AHUs are in place and remaining MEP/FP is ongoing.
Classrooms: Drywall is complete. Painting is ongoing. North classroom MEP/FP complete is complete; South classrooms is ongoing. ACT grid started last week. Flooring to start this week.
Maine West:
Down to just a few open punch-list and close out items. Signage/history wall scope to be completed this summer.
Construction Budget
Construction Budget update provided.