Select a School

Maine EastMaine WestMaine South
Maine EastMaine WestMaine South
Maine EastMaine WestMaine SouthAdmin

News

June 12, 2023
May 2023 Construction Update

NEIGHBOR RELATIONS

No neighbor issues to report.  

PROJECT SUMMARY – Current Progress

All 3 schools are fully occupied with small projects wrapping up at each location.

All schools will have punch-list, training, commissioning, and closeout work happening over the next several months.  

Maine East:  

All pool tile and accessories have been installed. The replacement tile for the pool deck has arrived and is scheduled to be installed the week of 5/8/23. Punch lists have been issued and items are being complete/corrected.

In the pool locker rooms all toilet accessories and bathroom partitions have been installed. Punch lists have been issued and are being complete/corrected.

MEP overhead work is substantially complete on the west side of the 3rd floor (Area B). Drywall partitions and soffits are upcoming.

Maine South:  

Continuing to work on punch list and closeout from previous phases.

Demolition in the auditorium to start May 18th.

Maine West

Down to just a few open punch-list and close out items.  Signage/history wall scope to be completed this summer.