NEIGHBOR RELATIONS
No neighbor issues to report.
PROJECT SUMMARY – Current Progress
All 3 schools are fully occupied with small projects wrapping up at each location.
All schools will have punch-list, training, commissioning, and closeout work happening over the next several months.
Maine East:
All pool tile and accessories have been installed. The replacement tile for the pool deck has arrived and is scheduled to be installed the week of 5/8/23. Punch lists have been issued and items are being complete/corrected.
In the pool locker rooms all toilet accessories and bathroom partitions have been installed. Punch lists have been issued and are being complete/corrected.
MEP overhead work is substantially complete on the west side of the 3rd floor (Area B). Drywall partitions and soffits are upcoming.
Maine South:
Continuing to work on punch list and closeout from previous phases.
Demolition in the auditorium to start May 18th.
Maine West:
Down to just a few open punch-list and close out items. Signage/history wall scope to be completed this summer.