- PROJECT SUMMARY
Current Progress
All 3 schools are fully occupied with small projects wrapping up at each location.
All schools will have punch list, training, commissioning and closeout work happening over the next several months.
Maine East:
Field house flooring is complete, floor striping is in progress. Painting work is ongoing. Turn-over of this space is scheduled for next week.
Ceiling drywall and taping has finished and painting is starting.
Pool locker room wall tile and lockers have started.
Maine South:
Pool work is complete and turned-over; final inspections this week.
Continuing to work on punch list, closeout and training items.
Maine West:
Working on punch list, training and close out items.
Construction Budget